In Microsoft Project (MSP), Percent (%) Complete is incorrectly showing as 99% for one or more tasks, while in Clarity it is showing as 100%. Another symptom reported is that the % complete is being calculated based on on start/finish dates, but it's expected the % Complete should be able to be set manually.
Release: All
Component: Clarity Microsoft Project Integration
This issue can happen if the MSP Option 'Updating Task status updates resource status' is checked. It is required to have this unchecked when integrating MSP with Clarity.