You have a task that is completed with no hours remaining and the finish date is defaulting to the actuals thru date in Microsoft Project (MSP) using the non-legacy interface. It's expected the finish date on completed tasks should remain whatever it shows in Clarity.
Expected Results: Task Finish date hasn't changed (shows the date for when actuals were submitted during August 2020 time frame)
Actual Results: Task finish date changes to actual thru date (in the above example, 7/9/21)
Release : 15.9.1
Component : CLARITY MICROSOFT PROJECT (MSP)
MSP Version impacted: Microsoft Project 2016 32 bit level version 16.0.7301.1019
This issue appears to be due to an issue with the Microsoft Project version used
Upgrade Microsoft Project to the latest available update. See Microsoft Project monthly patches impact with Clarity for more information regarding MSP updates.
Any assignment that exists in Classic PPM when a timesheet for that resource is posted gets an Actuals Thru date equal to the end of the timesheet period. Conditions can exist where you inadvertently place remaining work before this date. The following examples illustrate this condition:
When these situations occur, the work is moved beyond the Actuals Thru date when you save the project to Classic PPM. A message appears warning you of the change.