I have a task that is completed no hours remaining and the finish date is defaulting to the actuals thru date in Microsoft Project (MSP) using the non-legacy interface. It's expected the finish date on completed tasks should remain whatever it shows in Clarity.
Expected Results: Task Finish date hasn't changed (shows the date for when actuals were submitted during August 2020 time frame)
Actual Results: Task finish date changes to actual thru date (in the above example, 7/9/21)
This issue appears to be due to an issue with the Microsoft Project version used
Release : 15.9.1
Component : CLARITY MICROSOFT PROJECT (MSP)
MSP Version impacted: Microsoft Project 2016 32 bit level version 16.0.7301.1019
Upgrade Microsoft Project to the latest available update. See Microsoft Project monthly patches impact with Clarity for more information regarding MSP updates.