There is a resource whose rate is showing a different amount on the Resource Sheet in Microsoft Project (MSP) as compared to that defined in the Rate Matrix in Clarity.
The Rate Matrix Extraction job has been completing successfully and populating the NBI_PROJ_RES_RATES_AND_COSTS table in the database with the same unexpected rate as what MSP is showing.
Release : Any
Component: Microsoft Project (MSP) Interface
This can occur if the resource defined on the Rate Matrix is copied and pasted into the Resource field when adding the new row.