The Durations are changing to a shorter duration (Finish date is earlier then expected).Issue happen s when project is exported to Microsoft Project (MSP)
Release : All Supported Release
Component : CA PPM MICROSOFT PROJECT (MSP)
This issue can happen if the amount of work assigned to the resource during the duration is less then their available hours.
Example for a Resource assigned 10 hours of work for a 5 day duration Fixed Work task (With no actual work completed):
The task will be autosheduled to have the user work 8 hours on the first day of the task and 2 hours the second day which results in a 1.25 duration.
To keep the durations from changing: