When creating new tasks in the Microsoft Project (MSP) New Driver, after saving the file back to Clarity and re-exporting to MSP, the tasks move to the bottom of the project (or bottom of the summary task if added under a phase/summary task). Symptoms can also be seen if clicking F9 to update the MSP screen, where tasks will then end up out of order.
Steps to Reproduce:
Expected Results: The tasks remain in the same order (Task 5 displays in between Task 2 and Task 3)
Actual Results: The newly created task (Task 5) shows up at the bottom of the project
Release: All Supported
Component: MSP New Driver Integration for Clarity
This is due to a setting in Microsoft Project
See also: MSP: Copying entire task rows duplicates or moves some tasks regarding a defect impacting Clarity 15.7.1, 15.8, 15.8.1, 15.9, and 15.9.1
Additional Reference: