In the Microsoft Project (MSP) New Driver, any tasks/milestones added to the Timeline view are not preserved after saving the project to Clarity and reopening the project from Clarity to MSP.
Steps to Reproduce:
Expected Results: The task you added to the Timeline in Step 5 is still visible in the Timeline section
Actual Results: The task is no longer visible in the Timeline section
This issue applies to the MSP New Driver.
This issue is caused by a Microsoft Project limitation.
This issue is due to a Microsoft Project limitation with XML. This is verified by testing with Microsoft Project Standalone using the following steps:
Expected Results: The task you added to the Timeline in Step 4 is still visible in the Timeline section
Actual Results: The task is no longer visible in the Timeline section