Problem: After upgrading the DX UIM environment from 23.4.3 to 23.4.9, multiple hubs appear disconnected or "disappeared" from the Infrastructure Manager / Admin Console. Primary hub is tunnel clients for Remote hubs which are Tunnel Servers.
The hub.log file on the primary or affected hubs indicates a handshake failure due to weak signature algorithms: SSL error with certificate at depth 0 error: CA signature digest algorithm too weak (68)
How do I reestablish the connectivity?
DX UIM 23.4.7 and later
Starting with DX UIM 23.4.7, SSL tunnel communication requires SHA-384 hashing algorithms for all tunnel certificates. Certificates generated prior to 23.4.0 typically use SHA-1. When upgrading directly from 23.4.3 to 23.4.9, the hub strictly enforces this security policy, causing all existing SHA-1 tunnel connections to fail.
In this Scenario, the primary hub is upgraded to 23.4.8 or later while remote hubs are still running on hub 23.4.3 Version.
Immediate Workaround (Restore Connectivity):
hub probe folder on the affected hubs.hub.cfg file (or use Raw Configure).<hub> section, add: enable_cert_compatibility = yes.Permanent Remediation (Security Best Practice):
enable_cert_compatibility = yes parameter from the hub.cfg to enforce the higher security standard.