After an HCX Bulk Migration fails due to an underlying issue, an attempt to cancel or "Force Cleanup" the migration task results in the following error: "Cannot cancel migration. Migration is in Initial Sync Failed state."
VMware HCX 4.x
This error occurs because the migration workflow has entered a "stale" or locked state following the initial failure. When the user attempts to trigger a cancellation or cleanup, the HCX Manager cannot reconcile the current "Initial Sync Failed" state with the cancellation request, resulting in the migration task becoming trapped in the user interface.
Because the migration failed during the initial sync and did not progress further, the task can be safely removed by archiving the record.
If you require further assistance, visit our main Contact Broadcom support page or refer to Creating and Managing Broadcom Support Cases.
Important: This resolution applies only to migrations that failed during the initial sync phase where no data has been fully replicated.