Changing the NSX upgrade target version before the upgrade was started
search cancel

Changing the NSX upgrade target version before the upgrade was started

book

Article ID: 413345

calendar_today

Updated On:

Products

VMware NSX

Issue/Introduction

  • NSX upgrade was initiated from NSX version A by uploading a MUB or PUB file for NSX version B.
  • Upgrade prechecks may or may not have been completed.
  • Actual NSX upgrade was not started (neither of ESXi hosts, NSX Edge nodes, NSX Managers were upgraded).
  • There is a requirement to change the target of the upgrade from NSX version B to NSX version C.

Environment

VMware NSX
VMware NSX-T Data Center

Resolution

  • Upload the MUB or PUB file for NSX version C (just like you did for NSX version B).
  • The NSX Upgrade Coordinator will be upgraded from NSX version B to NSX version C.
  • You can resume the upgrade planning.

Additional Information

If the upgrade was started, please refer to this separate article: Changing the NSX upgrade target version in the middle of an upgrade