Project Baseline Usage Calculation
book
Article ID: 36108
calendar_today
Updated On:
Products
Clarity PPM SaaS
Clarity PPM On Premise
Issue/Introduction
How is the Project Baseline Usage calculated?
Environment
Any Supported Clarity Releases
Resolution
Project Baseline Usage displays the system-generated usage at the time you baseline using the following formula:
Baseline Usage = Total Labor Actuals + Total Labor ETC
Notes:
- Baseline Usage is the term used both by PPM and Open Workbench
- The equivalent of Baseline Usage in Microsoft Project (MSP) is Baseline Work
- The equivalent of Remaining Work in MSP is ETC
- To update this value for the Current Baseline rolled up to the Project level, run the 'Update Investment Allocations and Usage' Job with parameters
- When there are Subprojects, the Baseline details roll up to the Parent Project
Feedback
thumb_up
Yes
thumb_down
No