Sort changes to Unique ID instead of ID in Microsoft Project (MSP).
This can cause some tasks to appear to be displayed out of order in the project.
Release : All
Component : CLARITY MICROSOFT PROJECT (MSP)
Microsoft Project 2016
Ensure you are on the latest MSP version of MSP 2016. See Microsoft Project monthly patches impact with Clarity for details related to MSP Updates.