When trying to change an investment's start date to the 1st of January 2021, this is being reverted to the 9th of November 2020.
We are unable to set the Start date to any later date than the 9th of November.
The date is always reverted, regardless of the update being made by XOG, process or manually.
There was a timesheet posted on the 9th of November 2020 against that investment
The investment start date can not be set to a later date than the earliest posted actuals.
If time was posted against the other work instance on the 9th of November 2020, the start date will revert to that date
Even adjusting a timesheet and removing the wrongly posted actuals will not allow you to modify the investment start date