Question:
Upon launching a project to MSP, I am getting the following error:
"The element <ActualWork> in the <Assignment> element with <UID> = 9 has invalid data. The duration of this fixed duration task will change to accommodate the resource assignment"
This error pops up three times before MS Project finishes loading.
What does this mean?