In some projects, the hierarchy is not working as expected. The financial totals for all projects are not correct. There are subprojects with planned cost that sometimes do not show any cost (Showing 0.00 Values)
All Clarity Releases
Clarity Financial Management
This can be due to the Allocation % on the hierarchy page being set to 0%. The Allocation % field is used for the children and if the child is allocated to more than one program or subproject the amounts need to be adjusted as the total cannot be more than 100%.
On the hierarchy tab, click on the 0% in the Allocation field and then change the amount.
Note: If you click on the allocation, and the project is associated to more than one parent: You will have to put the percentages on each one. They must total 100%