Milestone finish date still shows the date prior to the update in Clarity. Unable to save a project back to Clarity 

STEPS TO REPRODUCE:

  1. Create a new project (11/25/2022 -> 11/25/2023)
  2. Create a new milestone task (11/25/2022)
  3. Open project in MSP
  4. Set the task to Manually Scheduled
  5. Save the project back to Clarity
  6. Change the milestone date to a different one (11/30/2022)
  7. Open project in MSP

Expected results: Start and Finish dates for the milestone are 11/30/2022. Project saves correctly.

Actual results: Start is 11/30/2022 and Finish is 11/25/2022 (previous date prior to the change). Unable to save the project back.

Environment

Reviewed and reproduced using:

  • Clarity 16.0.3 and 16.1.0
  • MSP 2019 16.0.15726.20202 (November 8, 2022)

Cause

DE67495

Resolution

This is not a Clarity issue.

This issue has been fixed by Microsoft in a Project patch: March 14, 2023 - (Version 2302 (Build 16130.20306)).

https://learn.microsoft.com/en-us/officeupdates/current-channel