When a user adds a named resource assignment to a task, the system creates the same assignment for the staffed Defined Team where this Resource is a member. This causes extra assignments for the Defined Team unexpectedly.
Steps to Reproduce:
Expected Results: Tasks to be displayed so they can be added to the timesheet.
Actual Results: No rows to Show is displayed.
Clarity Release: 16.0.1, 16.0.2
DE64608, fixed in 16.0.3 and 16.0.2.1
Workaround: Do not use the 'Group By' to select tasks. If the Defined Team is removed from the Project > Task > Assignments , the user will be able to navigate successfully.