A program containing child projects display those projects as tasks. For a project, the baseline start and baseline finish dates are empty, even though the project has a baseline.
Release : 15.8.1
Component : CA PPM SAAS PROJECT MANAGEMENT
Baseline attributes, such as Baseline Start or Baseline Finish, display data for the current instance baseline. However, a program cannot have a baseline, so these values will be empty.