Task with Duration can be converted to Milestone using MSP
search cancel

Task with Duration can be converted to Milestone using MSP

book

Article ID: 213368

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

In MSP, it is possible to have milestones that have multiple days duration, but it is against Clarity definition of a milestone (it should also not have assignments nor actuals). Saving a project with milestones that do not fulfill these conditions is possible from MSP to Clarity.

Steps to Reproduce:

  1. Create three new tasks with 1 month duration
  2. Assign a resource to two of the tasks
  3. Post a timesheet for that resource for one of the tasks, so that the task has actuals
  4. Open the project in MSP
  5. Select the three tasks, and check "Mark task as milestone"
  6. Save to Clarity

Expected results: Save fails. Milestones in Clarity are expected to start and finish the same day (no duration).
Actual results: Project is saved successfully. Clarity now have 3 milestones with 1 month duration, 2 milestones with assignments and 1 milestone with assignments and actuals.

Environment

Release : All

Component : CLARITY MICROSOFT PROJECT (MSP)

Cause

There are some features from MSP that Customers expect to work even when they are integrated with Clarity.

The current design allows Milestones that come from MSP to have durations longer than zero (i.e.: start and finish dates are not the same), assignments, and/or actuals.

Resolution

Clarity will not allow toggling the Milestone checkbox (it will be grayed out, read-only) once it contains assignments or actuals. This can be switched again opening the project in MSP and saving the project back.

In order to restrict this functionality via the Clarity - Microsoft Project integration (for example, with a toggle to enable/disable this behavior), it would be necessary to work on this as an Enhancement.