Unable to save task duration changes / modify the Duration field on a task. This happens even if the task is set to fixed duration, and not locked for scheduling. The behavior varies based on the area of Clarity:
The only thing that seems to change the duration field if not using the Gantt is changing the dates. Is this by design?
Expected Results: Value does not change back to 1
Actual Results: Value changes back from 7 to 1
This issue is working as designed.
Release : All Supported
Component : Clarity Project Management
The one option to change the duration without changing dates is to use the Classic Gantt (or change the dates of the task instead of modifying the duration).