Is there a way to map the Task Owner field's data to Microsoft Project (MS Project) so that when I download a project, the task owner information also gets downloaded along with the tasks?
Release : 15.7.1 and Higher
Component : CA PPM PROJECT MANAGEMENT
4. Click Save and Return
Note: It's not possible to use Data Operation options of Import or Import and Export, as the Task Owner data is not able to be saved back from MSP.
See also: Task Owner field: What is it used for?