Issue/Introduction

The ETC hours on various task assignments are getting reduced. 

Environment

Release : All

Component : CA PPM Project Management

Resolution

This will occur if the task Loading Pattern is Fixed and actuals get posted for the resource. Once actuals get posted, the Actual Thru date gets updated on the task assignment, and any remaining ETC hours previous to this date will be zeroed out.