Project Management Schedule Dashboard and Project Management Cost and Effort Dashboard deprecated portlets (PostgreSQL)

book

Article ID: 194697

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

After the GCP migration, when we try using the portlets:
Project Management Schedule Dashboard 
Project Management Cost and Effort Dashboard 

we get error messages. What should we do? 

Environment

Release : 15.8+

Component : 

Resolution

These portlets are deprecated and should be removed and replaced.

 

How to replace the deprecated portlets with the current portlets:

The Project Management Schedule Dashboard portlet should be replaced by the Schedule Dashboard (cop.prjScheduleDashboard)

The Project Management Cost and Effort Dashboard should be replaced by the Cost and Effort Dashboard (cop.prjCostEffortDashboard)

 

1. Navigate to Administration > Studio > Portlet Pages and search for the Overview page (niku.overviewFrame). Open it.

2. Navigate to Tabs tab and click on the Project Dashboard tab (link to the tab)

3. Navigate to Content tab and remove both portlets

4. Add the correct portlets marking the Schedule Dashboard as the Maximized portlet:

 

5. Navigate to Page Filters tab and remap filters as follows:

6. Save and publish it.