Unable to edit Task ETC in Modern UX in Assignment module
search cancel

Unable to edit Task ETC in Modern UX in Assignment module

book

Article ID: 193260

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

If the ETC gets down to zero (from Actuals posted), then ETC totals column can not be updated in Assignments module

STEPS TO REPRODUCE: 

Prereqs
Project open for time using a blueprint with the Assignments module.
Resources added to Project Open for time
Tasks added to Project Open for time
Total ETC column in Assignments module

 

1.  In Project add 8 ETC in the ETC Total column to the assignment

2.  Create Timesheet and add 8 to the tasks assigned

3.  Submit, Approve and Post timesheet

4.  Go back to Project>>Assignments and see ETC Total column is 0

5.  Try to update ETC Total column.  

Expected Results - ETC updates

Actual results - You are able to enter in ETC but when tabbing out, the number is removed.

Environment

Release : 15.8, 15.8.1

Component : CA PPM PROJECT MANAGEMENT

Cause

DE55743

Resolution

This is NOT reproduced in 15.9

Configured the TSV 'Total ETC' and Period ETC fields on the ASSIGNMENTS Module. The 'Total ETC' amount could be updated.