There are a couple of projects that have zero actual hours, as well as a $0 ACWP amount. However, it's expected that both of these values be greater than 0.
Release: All Releases
First, the resources must have a rate for the project. For this, the project needs to be associated to a rate matrix, if not already, and the Rate Matrix Extraction job will need to run.
The approved timesheets with time against these projects will then need to be posted by running the Post Timesheets job.
For Usage and Current Baseline data at the investment level run the 'Investment Allocation' job.