When changing the 'Week starts on' setting in Microsoft Project (MSP) (under File - Options - Schedule) and saving this project back to Clarity, the next time the project is exported to MSP, the setting is reverted back to the previous setting. For example:
Results: The 'Week starts on' is reset back to Monday.
Release : All
Component : Clarity Microsoft Project Interface (MSP)
The 'Week starts on' setting in MSP is pulled from the 'First Day of Work Week' setting in Clarity (under Administration - Project Management - Settings) so any changes made to this setting in MSP will not save back to Clarity. If the 'First Day of Work Week' setting is set to Monday in Clarity, the 'Week starts on' setting in MSP will always default to Monday when exporting a project to MSP.
See Define Default Project Settings on techdocs where this is referenced.
For required and recommended settings in working with the Clarity MSP Interface, see: Configure default settings in MSP to use with Clarity