Issue/Introduction
Where the Data Warehouse fields in DWH_INV_SUMMARY_FACTS come from:
EAC_TOTAL_COST
ACTUAL_COST
Environment
Release: Any Supported Release
Resolution
DWH_INV_SUMMARY_FACTS table:
- EAC_TOTAL_COST Total estimate at completion cost from assignments.
- It will take and add data from the combined assignments on the investment.
- ACTUAL_TOTAL_COST Total actual cost from financial transactions.
- ACTUAL_LABOR_COST Actual cost from financial transactions where the transaction type is Labor.
- ACTUAL_LABOR_HOURS Actual labor hours from assignments.
- The data gets collected from Assignments, and then summarized to Investment level.