Task / assignment dates impact with Timesheet population in Modern UX
book
Article ID: 124319
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
How do Task / Assignment Start Finish dates impact Timesheet Population in the Clarity New User Experience / Modern User Experience (NUX/MUX)?
These scenarios include the below timesheet creation options:
Add Assigned Tasks
Copy Previous Timesheet
Copy Previous Timeheet with Hours
Environment
Release: Component: PPMTMM
Resolution
If the timesheet is created using the Add Assigned Tasksfeature:
Here are scenarios where the task will still show up even if the time period is not within the assignment start/finish dates
The task is added if the time period falls within the system timesheet population window set in Clarity in Administration->Timesheet Options. (Whether ETC on the task is 0 or not).
The application also shows tasks with non-zero remaining ETC in time periods that occur after the assignment finish date
If the timesheet is created using the Copy Previous Timesheet feature:
If the task was on the prior timesheet, the task will get added using this feature.
If the timesheet is created using the Copy Previous Timesheet (with Hours) feature:
If the task was on the prior timesheet, the task (and the hours from the previous task) will get added using this feature (providing the day being copied from (or to) is not a non working day).