KB |
Scenario |
Add Assigned Tasks |
Copy Previous Timesheets |
Copy Previous Timesheet (WITH hours) |
Tasks with no ETC, tasks that have ETCs (non zero ETC), tasks with Pending ETCs |
If there is ETC on the task, the task is added to the timesheet if the task assignment dates fall under one of the below criteria (See KB: KB000124237):
If there is no ETC on the task, the task is added if it falls within the Populate Time Range set in Administration->Timesheet Options |
The behavior would be the same for all ETC Scenarios. |
The behavior would be the same for all ETC Scenarios. The task and hours will copy over even if the time period of the timesheet is not within the Populate Time Range set in Administration->Timesheet Options. (Hours copy over providing that the day the hours are copied from or to are NOT Non working days) | |
Start/Finish Dates of Task Assignments |
The task will still show up even if the time period is not within the assignment start/finish dates if the task assignment dates falls within the system timesheet population window set in PPM in Administration ->Timesheet Options. (Whether ETC on the task is 0 or not). The application also shows tasks with non-zero remaining ETC in time periods that occur after the assignment finish date |
If the task was on the prior timesheet, the task will get added using this feature. |
If the task was on the prior timesheet, the task and it’s hours will get added using this feature (providing the day being copied from or to is not a non working day). | |
Working day / Non working day |
The task behavior is the same for Non Working Days versus Working days. |
The task behavior is the same for Non Working Days versus Working days. |
Hours are not copied over for non working days. See KB KB000124318 for more details. | |
Project open for time entry setting |
The task will not get added unless the project is open for time entry. |
The task will not get added unless the project is open for time entry. |
The task will not get added unless the project is open for time entry. | |
Tasks open for time entry setting |
The task will not get added unless the task is open for time entry. |
The task is added when the timesheet is created using this feature. |
The task and previous hours enter are populated using this feature. (Providing the Task being copied from or To is not a Non Working day | |
Other Work |
All other work tasks the resource is allocated to during the current time period would copy over. |
By design, only other work items on the previous timesheet should copy over. See KB000124283 for more details on a defect that may cause unexpected Other Work items to also be populated. |
By design, only other work items on the previous timesheet should copy over. See KB000124283 for more details on a defect that may cause unexpected Other Work items to also be populated. | |
Time periods that vary (example, one week the time period starts on Monday the next one it starts on Wednesday) |
n/a |
n/a |
The copy hours from previous timesheet doesn't look at the day of the week but looks at the cell / column order. |