PPM: Tasks saved in OWB automatically become Milestone

book

Article ID: 122211

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS - Application Clarity PPM On Premise

Issue/Introduction



When save Task which has same Start and Finish date in Open Workbench,  it becomes Milestone automatically.
Why Open Workbench changes Task to Milestone?

Environment

Release:
Component: PPMOWB

Resolution

If task is defined with Duration=0 and Fixed is selected, it will be Milestone.

Replication steps:
1. create task with duration 1 day and define same date for start and finish.

<Please see attached file for image>

User-added image

2. change Duration 0 day and turn on Fixed checkbox.

<Please see attached file for image>

User-added image

3. save and task will be changed to Milestone.

<Please see attached file for image>

User-added image