Task status and % Complete cannot be changed and there is a mismatch in the two values
search cancel

Task status and % Complete cannot be changed and there is a mismatch in the two values

book

Article ID: 103484

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

Some tasks in Clarity PPM are not being able to be edited to be set to "Completed" or the % complete is changed to 00% but the status still says "Started" and cannot be edited to "Completed" while other tasks are not facing this issue. 

Cause

  1. The issue with task status and % Complete not being editable can happen if the % Complete Calculation on the Project is set to Effort and there are any non Labor Resources assigned to the task.
  2. Additionally, the issue with task status changes not saving even if the % Complete calculation of the project is set to Manual can be due to there being ETC left on the task. 

Resolution

For the % Complete Calculation Method of Effort, non labor resources are not included in the calculations. In order for the task % Complete and Statuses to be able to changed, the project % complete calculation method would need to be Duration or Manual. Note: It is not recommended to change a % Complete Calculation Method of a project once it's been set as this can impact the task data. 

Note: Even if the % Complete Calculation Method of the project is set to Manual, in order to be able to save a task status of Completed, there must be 0 ETCs on the task.