First baseline creation by process is not mark as current revision.

book

Article ID: 8729

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

A process is able to create a new baseline revision without marking it current when no existing current revision is present.

Because of that, the baseline is not displaying some baseline information on tasks like  'Baseline Start' and 'Baseline Finish' attributes.

Example:

  1. Create a simple process that baselines a project.  The action should be:
    1. Baseline the project
    2. Create a NEW revision
    3. Mark revision ‘current’:  NO
  2. Run the process on a project with tasks but NO BASELINES

 

Expected Results:  Tasks displaying all baseline information.

Actual:  Task is not displaying all baseline information ex ('Baseline Start' and 'Baseline Finish').

 

 

 

 

Cause

Reported to Engineering: DE37439 

 

 

Environment

All CA PPM Versions.

Resolution

Defect DE37439 Resolved in 15.4.

 

Workaround: Mark the baseline created by the process as "Current Revision" and this will correct the display. 

Additional Information

Reference: How is Baseline Usage Calculated?