Estimated runtime (ERT) is incorrectly calculated in conditions in V11.2
search cancel

Estimated runtime (ERT) is incorrectly calculated in conditions in V11.2

book

Article ID: 87250

calendar_today

Updated On:

Products

CA Automic Workload Automation - Automation Engine

Issue/Introduction

Error Message :
U00011545 Max. runtime of task '%' (RunID '%') has been exceeded. Task will be canceled or terminated respectively.
or
U00011544 Max. runtime of task '%' (RunID '%') has been exceeded. Task '%' will be started.

When attempting to utilize Estimated runtime (ERT), such as an ERT +%50 value for Maximum runtime (MRT), a "runtime of task has exceeded" error similar to one of the above errors may appear when the Job has not reached the max defined ERT value. 

Environment

Release: AUTWAB99000-11.0-Automic Workload Automation-Base Edition
Component:

Cause

Cause type:
Defect
Root Cause: A problem has been identified where ERT options set in UC_CLIENT_SETTINGS (ERT_METHOD,...) are not considered in the ERT calculation. The default values are used.

Resolution

Update to a fix version listed below or a newer version if available.

Fix Status: Released

Fix Version(s):
Components: Automation Engine, Database.

Automation Engine 11.2.5 HF2 - Available

Additional Information

Workaround :
Set ERT options directly in objects.