Invalid Processing Date in response to Dollar UORDRE command from Z/Os Manager 3.0.02
search cancel

Invalid Processing Date in response to Dollar UORDRE command from Z/Os Manager 3.0.02

book

Article ID: 86876

calendar_today

Updated On:

Products

CA Automic Dollar Universe

Issue/Introduction

Error Message :
Invalid Processing Date

Patch level detected:Manager for MVS 3.0.02
Product Version: Dollar.Universe 6.0.0

Parameter PDATE not validated in the $UORDRE command.

When submitting a job from z/OS Manager to Dollar Universe using $UORDRE containing the parameter PDATE, the error message "Invalid Processing Date" results.

Environment

OS: MVS
OS Version: N/A

Cause

Cause type:
Configuration
Root Cause: Problem was the omission of final - on the value of the parameter PDATE.

The syntax given in the documentation named MVS_30_en.pdf works properly:

Parameters:
All the parameters are entered in SYSIN in the following order:
NODE= -
COMPANY= -
AREA= -
MU|UG= -
TASK= -
DTRAIT|PDATE= -
AFTER="" -
ELAPS="(hhhmm)" -
EXCLU=(hhmm,hhmm) -
QUEUE= -
PRINTER= -
FORCE|NOFORCE -
BYPASS -
VAR=:"" –

Resolution

Add the final - after the value set for the processing date.

Fix Status: No Fix

Fix Version(s):
N/A

Additional Information

Workaround :
N/A