Error Message :
N/A

Patch level detected:Univiewer Console 6.1.00
Task's workload forecast calculation method is not correct. Forecast average running duration is 2 times the running time in Statistics. This issue makes the forecast inaccurate.

Product Version: Dollar.Universe 6.1.0

Cause

Cause type:
Defect
Root Cause: N/A

Environment

OS: All

Resolution

Update to a fix version listed below or a newer version if available.

Fix Status: Released

Fix Version(s):
Dollar Universe 6.2.21 - Available