Description :When opening a job chain, it displays the 'start date' for all runs. If holds one of the run, then it will display the 'end date' instead.
Cause
Cause type: By design Root Cause: This is a normal behavior of Univiewer Console.
Environment
OS: Windows Seven
Resolution
Because there is only one line for the date in the job chain graphic,it was decided to use the end date instead of start date for "Hold" uproc.