Schedule objects do not process period-turnaround if schedule in status STOPPED_QUEUE
book
Article ID: 85062
calendar_today
Updated On:
Products
CA Automic Workload Automation - Automation Engine
Issue/Introduction
Error Message : N/A
Tasks within Schedule are activated after the start time has been exceeded under specific conditions.
Schedule objects do not process their period-turnaround if the schedule is in a status of STOPPED_QUEUE.
Period turnaround is processed when the queue is set to GO again.
Investigation
Create JOBP with 1 task inside.
Create Schedule object
Add the JOBP to the schedule 6 times. Once at 22:00, 23:00, 23:30, 1:00, 2:00 and 3:30
Executed Schedule before 22:00
Stop Queue used by Schedule
Restart Queue next day after 3:30
Environment
OS Version: N/A
Cause
Cause type: Defect Root Cause: Schedule objects did not process their period-turnaround if the schedule is in status STOPPED_QUEUE. Period turnaround is processed when queue is set to GO again.
Resolution
Update to a fix version listed below or a newer version if available.
Fix Status: Released