Remote job log not purged in DQM with remote physical queue
book
Article ID: 84699
calendar_today
Updated On:
Products
CA Automic Dollar Universe
Issue/Introduction
Error Message : N/A
In a DQM configuration with a local generic queue (submission) and remote physical queue(s) (execution) the job log is not purged on the remote node.
In a scenario where the physical queues are local the job log is purged at the same time as the entry in the launch files according to the variables<X|S|I|A>_O_PURGE_* (e.g. X_O_PURGE_HST_RET_E).
In the remote case no purge is taking place.
Environment
OS: All OS Version: N/A
Cause
Cause type: Defect Root Cause: This is an omission
Resolution
Update to a fix version listed below or a newer version if available.
Fix Status: Released
Fix Version(s): Dollar Universe 6.9.01 - Available
Additional Information
Workaround : The remote job logs have to be removed manually or using a script.