Affects Release version(s): 5 and 6
Error Message :
In the "universe.log" file:
#########
Calendar not in range
#########
After the modification of the General Calendar, the Tasks are not scheduled/launched anymore.
Cause type: Configuration
Root Cause: The validity date defined in the Task is defined at a date prior to the start date of the modified Calendar.
First, move all Validity Dates forward (to e.g. the first day of the current year).
Then, set the Start Date to the beginning of the current year and extend the End Date of the Calendar as required to include at least current year +2