Schedule Object (JSCH) cancelled using "Cancel Recursive" goes into status "ENDED OK" and executes Tasks after cancellation
book
Article ID: 84362
calendar_today
Updated On:
Products
CA Automic Workload Automation - Automation Engine
Issue/Introduction
Error Message : N/A
A schedule object which is cancelled using the function "cancel recursive" goes into a status of "ENDED_OK" but still activates tasks within it:.
Note: This issue has been seen in Version 12.0.1, 12.0.2 and 12.0.3, however it is not reproducible in 12.1.
<Please see attached file for image>
It is not recommended to use this function for now until this is fixed.
Environment
OS Version: N/A
Cause
Cause type: Defect Root Cause: Schedule objects were not deactivated automatically after cancelling recursive. Schedule is still shown in process monitoring with state ENDED_OK.
Resolution
Update to a fix version listed below or a newer version if available.
The Solution is either to use Version 12.1 where the issue was not been reproduced, or to wait for a fix which is currenty in progress while using the described workaround until then.
Fix Status: Released
Fix Version(s): Component(s): AE Server and Initialdata
Automation Engine 12.0.4 - Available
Additional Information
Workaround : Use the "Quit" option for the schedule object instead. It works as expected and will result in no further tasks being executed from that schedule object.