OWB: can we control the default value of the task status when this is set to "Started"?
book
Article ID: 76857
calendar_today
Updated On:
Products
CLARITY PPM FOR ITGCLARITY PPM FEDERALClarity PPM SaaS - ApplicationClarity PPM On Premise
Issue/Introduction
In OWB, when you change the task status from "Not started" to "Started", the % Complete remains at 0%. This is not logical. Is there a way to control the % Complete value when the task status becomes "Started"?
Environment
Any PPM release
Resolution
You can map the Started status to a value you wish by: 1. Open OWB 2. Go to Main menu in OWB -> Project Properties -> Advanced 3. Set the '% Complete at Start' value to a figure you wish, e.g. 1%.