When having a project with resources using multiple calendars, the Standard Calendar is not loaded as the Project Calendar in MSP when using the New Driver.
Steps to Reproduce:
0. In an environment with resources using two calendars (Standard, the actual standard calendar), and another one, with different shift (7.5h), '7.5 Calendar'.
1. Create a project in PPM
2. Add resources that have both the 'Standard' (standard) calendar and the '7.5 Calendar' to the project team
3. Create tasks and assign one resource to each task
4. Open the project in MSP
5. Check MSP > Project > Properties > Project Information
Expected Results: Calendar shows as 'Standard'
Actual Results: Calendar shows as '7.5 Calendar'
Caused by CLRT-80941
This issue is fixed in CA PPM 15.1.0.1 and 15.2.