In the MSP New Driver, the Standard Calendar is not respected when a project includes resources using multiple Calendars

book

Article ID: 7061

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS - Application Clarity PPM On Premise

Issue/Introduction

When having a project with resources using multiple calendars, the Standard Calendar is not loaded as the Project Calendar in MSP when using the New Driver. 

 

Steps to Reproduce: 

0. In an environment with resources using two calendars (Standard, the actual standard calendar), and another one, with different shift (7.5h), '7.5 Calendar'. 

1. Create a project in PPM 

2. Add resources that have both the 'Standard' (standard) calendar and the '7.5 Calendar' to the project team

3. Create tasks and assign one resource to each task 

4. Open the project in MSP 

5. Check MSP > Project > Properties > Project Information

Expected Results: Calendar shows as 'Standard'

Actual Results: Calendar shows as '7.5 Calendar'

Cause

Caused by CLRT-80941

Environment

CA PPM 14.4 and 15.1

Resolution

This issue is fixed in CA PPM 15.1.0.1 and 15.2.