When exporting a project to Microsoft Project (MSP), external dependency Baseline Start/Finish dates are displayed as NA instead of the baseline dates for the task.
Steps to Reproduce:
4. Export Project1 to MSP
5. Add Baseline Start and Baseline Finish columns to the MSP View
Expected Results: The Baseline Start and Baseline Finish dates are displayed for the external dependency task from Project2
Actual Results: The Baseline Start and Baseline Finish dates for the external dependency task from Project2 are displayed as 'NA'
This is due to current Microsoft Project design.
This issue was reviewed as DE34428 and it has been determined to be working as currently designed by Microsoft Project.
This can also be reproduced in Microsoft Project Standalone using the below steps:
Results: Baseline Start and Baseline Finish dates are NA for the external dependency task.
Note: This limitation applies to team/assignments as well. They will not export with the project, but ETC (Remaining Work) in MSP will.