Task Dependencies are not automatically saved on local MPP files
search cancel

Task Dependencies are not automatically saved on local MPP files

book

Article ID: 6711

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

Task Dependencies are not automatically saved on local MPP files using the MSP New Driver.  

Steps to Reproduce: 
1. Create a new project in PPM
2. Add two tasks (T1 and T2)
3. Make T1 be a predecessor of T2 in PPM
4. Export to MSP using the New driver. The dependencies show.
5. Close out of MSP.
6. Go to My Documents
7. Open the project mpp 

Expected Results: t2 still shows t1 as its predecessor.
Actual Results: t2 has no predecessors.

Environment

CA PPM 14.4, 15.1, 15.2

Cause

Caused by DE33700

Resolution

DE33700 has been fixed on CA PPM 15.3. 