In the MSP, Unable to Save changes to the Project Calendar.
Steps to Reproduce:
Expected Results: The exception added (4/3/17 in this example) is still shown
Actual Results: The exception is no longer displayed
Any supported Clarity release.
This is working as designed.
This is working as designed as the concept of a project calendar does not exist in Clarity. Clarity uses the Standard calendar for the majority of its scheduling (when the autoschedule job is run). Also, Clarity is a resource based scheduler, so the calendars used in scheduling are only the ones that are associated to resources on that project team. These changes were made to the new driver in order to align the MSP Interface functionality with the way Clarity works.
To workaround this behavior:
1. Edit calendar at the resource level:
2. To make a change for multiple resources at the same time, you can create a calendar on the admin side and set the Non Work-Day exceptions there: