Export to excel fails when exporting the project list
Any CA PPM release
Initial troubleshooting if a list view export fails.
Remove as many columns as possible and try the export.
Re-add the columns one by one until you find out where the issue occurs.
It might happen when the start / finish field or any other date field is added
The export error will add similar entries to the log files:
XML ERROR in Table
REASON: Bad Value
FILE: C:\Users\~\Server\Project_List.xls
GROUP: Cell
TAG: Data
VALUE: 0201-12-31
This being the case, proceed as follows:
Through the project list options, go to Configure > List Column Section > Fields
Edit the properties of the field and set the Date/Time Format Scale to Year
Save and Return
On the project list click on the Start column header to order the list based on the year
Check the earliest and latest date.
You might find a start date pointing to year 0201 instead of maybe 2010. Ensure year date is correct and correct any typos.
Correct the wrong dates and set the as appropriate
The export to excel will now work