Why is the task start or finish date read-only?
search cancel

Why is the task start or finish date read-only?

book

Article ID: 58058

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

The task start date becomes read-only when actuals have been posted against the task.

The task finish date is governed by the ETC on the task. When ETC becomes 0, task is considered as complete and therefore the finish date becomes read-only

Environment

Release: All Supported Releases

Resolution

Add ETC on an assignment and Save.

After an assignment has ETC, the Start/Finish dates will be editable.