Can a user choose to re-baseline dates or hours on a task but not both
search cancel

Can a user choose to re-baseline dates or hours on a task but not both

book

Article ID: 55282

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

Description:   
Can a user choose to re-baseline dates or hours on a task but not both?

 

Solution:  
Users are not able to edit portions of the baseline information. Once a baseline is taken, all the information for the baseline gets updated. You may not pick and choose which parts, such as  dates, hours, or any other attribute on a task to get updated.

 