In Clarity on the Work Breakdown Structure (WBS) page the actuals do not match what MSP has, or the total on the Project Dashboard page.
search cancel

In Clarity on the Work Breakdown Structure (WBS) page the actuals do not match what MSP has, or the total on the Project Dashboard page.

book

Article ID: 53668

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

Description:

Tasks with actuals were changed to milestones in MSP, and then saved back to Clarity. The WBS page does not roll up actuals from milestones to summary tasks.

MSP supports actuals on milestones, but Clarity does not.

 

Environment

Release: NCSVCS05900-8.1-Clarity-Service Connect-for MS-SQL
Component:

Resolution

Solution:

Open the project in MSP. For any task with actuals and the Milestone field set to Yes, change it to No. Save the project back to Clarity.

In Clarity, if a milestone had an assignment you cannot access the Milestone field, it is not active. The change needs to be made in MSP.