Description:
The calculation is the task finish date - task baseline finish date.
There is a bug with the NSQL query for the Late Tasks and Milestones. The query is looking at the baseline finish date from the prtask table, instead of the prj_baseline_details table.
Solution:
Status:
Fixed in PMO 1.3
Upgrade to PMO version 1.3. If you cannot upgrade at this time you can XOG in the attached file to fix the NSQL query.
Keywords: CLARITYKB, PMO-278, Late Tasks and Milestones, Days Late, Portlet, pmo11open, pmo12open.