Description:
Details:
When copying tasks from a template, if resources are assigned to the task that are copied, the resources do become team members, they do not become
participants, even if they are participants on the template.
Steps to Recreate:
Expected Result: See the resource created in step 1 listed as a participant in Project B.
Actual Result: Resource created in step 1 is not listed as a participant in Project B.
Solution:
Manually add resources as participants to the project(s).
Status\Resolution:
This issue has been documented as CLRT-52821 and is assigned to development for review. If you are experiencing this issue and the workaround does not significantly help, please contact CA Clarity Support.
Keywords: CLRT-52821, Participants, Template, Copy, Clarity12open, ClarityKB